Question

Manage Replacements in multiple BOM

Matteo_1987_0-1701258637713.png

Is it possible to use manage replacement operation in more BOM?

2 replies

Nov 29, 2023 12:21 PM UTC

Hi @Matteo_1987 

As I know this is not possible,

This function is available just in one BOM. 

If you need to replace part in multiple bom you have to use a change notice process where you can do a multiBom change. 

PetrH

Nov 29, 2023 1:02 PM UTC

Hi Petr,

using mass change the replacement occurs immediately as if you used the replace with existing part command. The manage replacements function, on the other hand, indicates using the replaced component once the initially existing one has been used up.

 