Skip to main content
Jul 17, 2025 4:39 PM UTC
Solved

Windchill MBOM Save-As

My company makes custom filter equipment for each order. We are experimenting with EBOMs within WC. We would be making new MBOMs for every piece of equipment because no two are the same. Is there a way to Save-As both the EBOM and MBOM at the same time? I know you can Save-As the EBOM but that would require an MBOM to be remade for every single WTPart structure. Is there preference or setting I am missing?

Aug 7, 2025 8:06 AM UTC

Hello @RB_10499063 

One action method does not exist.

Here is the idea where you have an example how to create a copy eBOM with mBOM also with associated process plan.

https://community.ptc.com/t5/Windchill-Ideas/MPMLink-Process-Plan-Save-As-BOM-with-Process-Plan/idc-p/913782#M16872

The video shows how to save as mBom with new saved eBom 

 

It is not one click solution, but it is solution. In the past there were not this mBOM save as option. 

 

PetrH

6 replies

Jul 17, 2025 7:53 PM UTC

 I think without customization, its a two step process. Creating the MBOM from the EBOM, initially, they start out exactly the same.

Aug 1, 2025 1:55 PM UTC

are you using mpmllink to create the mbom in windchill? 

Aug 7, 2025 8:06 AM UTC

Hello @RB_10499063 

One action method does not exist.

Here is the idea where you have an example how to create a copy eBOM with mBOM also with associated process plan.

https://community.ptc.com/t5/Windchill-Ideas/MPMLink-Process-Plan-Save-As-BOM-with-Process-Plan/idc-p/913782#M16872

The video shows how to save as mBom with new saved eBom 

 

It is not one click solution, but it is solution. In the past there were not this mBOM save as option. 

 

PetrH

Aug 7, 2025 6:01 PM UTC

Thank you for the reply. I will send that potential idea forward.

 

To add to this, is it required for the eBOM to be released before we can create the mBOM? Forcing two separate CNs to go thru the process?

Aug 8, 2025 6:14 AM UTC

Hi @RB_10499063 

The release operation is not needed generally, but it depends on your lifecycle configuration or company needs.

PetrH